Question 1

A data center migration project has been selected and a project manager assigned. What should happen FIRST to give the project formal standing?

Question 2

An FPIF contract has target cost $1,000,000, target fee $100,000, ceiling price $1,265,000, and an 80/20 buyer/seller share ratio. What is the Point of Total Assumption?

Question 3

A stakeholder asks you to slightly misrepresent progress in the status report to buy time with the board. What should you do?

Question 4

Mid-project, the board redirects investment to a different market segment. What should you do FIRST?

Question 5

BAC = $1,000,000, EV = $500,000, AC = $600,000. What is the To-Complete Performance Index, and what does it mean?

Question 6

A stakeholder demands daily one-on-one updates from you, consuming two hours a day. What should you do?

Question 7

The project's success depends on a partner organization's deliverable, and the partner is deprioritizing it. What is the best approach?

Question 8

The seller will be paid for time worked plus materials, but the buyer sets a ceiling price. Which contract type is this?

Question 9

The sponsor directs a priority change that the team believes will harm the product, and the team looks to you. What do you do FIRST?

Question 10

Your project deploys an e-commerce platform subject to consumer-protection laws in twelve countries. What is the BEST compliance strategy?